Most solar projects that miss their dates did so for reasons that were visible months earlier. For example: a late equipment order, a rushed soil investigation, or a utility order that took weeks instead of days. Each of these problems is manageable when someone owns it early, and each becomes expensive when it first appears during construction.
In our experience, there are six common areas where commercial and utility-scale solar and storage projects most often lose time or money.
1. Interconnection takes longer than the contract assumes
Interconnection is the utility approval and physical connection that allows a project to deliver power to the grid. Berkeley Lab’s Queued Up report found that only 13% of the capacity that entered U.S. interconnection queues between 2000 and 2019 had reached commercial operation by the end of 2024, while 77% had been withdrawn. A follow-up release from the lab reports that the median time from request to a signed interconnection agreement was well over three years in 2025, and that reaching commercial operation takes more than five years in the regions with available data.
Those figures describe transmission-level queues, which mostly affect larger projects. Commercial projects often connect at the distribution level instead, and in California that process is governed by Rule 21. In late 2025, 18 California legislators asked the CPUC to enforce Rule 21 timelines, and documents cited in the coverage put utility non-compliance with certain deadlines as high as 73% over five years.
The effect on a construction schedule is direct. Crews, equipment, and financing are lined up against an energization date that the utility controls, so when that date moves, the owner pays for idle assets. Utility studies also define scope, such as service upgrades, protection requirements, or medium-voltage work between the utility’s connection point and the customer’s equipment. A contractor with electrical expertise can read that study when it arrives, turn it into a construction scope and schedule, and flag conflicts while there is still time to resolve them.
2. Subsurface conditions surprise projects that rely on thin geotechnical data
Geotechnical investigation is the soil and rock testing that tells designers what lies under a site. Burns & McDonnell notes that nearly half of solar construction happens underground, and that owners who invest in a proper investigation early reduce change orders and receive more accurate bids.
The risk concentrates in pile foundations, the steel posts driven into the ground to support racking or trackers. DNV, an independent engineering firm, explains that a 300 MW project can involve around 100,000 piles, so any delay in driving them affects the whole schedule. If the investigation did not include enough borings, hard layers such as rock or caliche can cause hundreds of pile refusals. A refusal occurs when a pile stops advancing before it reaches design depth. Terrasmart defines it as less than 12 inches of progress in 30 seconds, or an installation that takes more than five minutes.
Refusals cost more than the foundation crew’s time. In one Terrasmart analysis of a 10 MW site, the effect on other contractors and support services reached up to $25,000 per week. Terrasmart sells foundation systems, so that figure is one vendor’s scenario. It does match DNV’s independent guidance that foundation surprises are expensive and that the remedy starts with better data before construction.
Civil work also determines whether the electrical work can start on time. A team that performs its own earthwork, trenching, and concrete reads a geotechnical report with production rates in mind. It can price pre-drilling or alternate foundations before the first pile is driven, and it can sequence grading, drainage, and equipment pads so electrical crews are never waiting on a civil crew.
3. Civil and electrical scopes get handed off between parties
On many projects, civil work, electrical work, and solar installation are bid and managed as separate packages. Each package can meet its own specification and still fail at the boundary. An equipment pad poured to one drawing revision may not match the switchgear that was finally ordered. A trench route may conflict with a late drainage change. Conduit stub-ups, grounding, and cable pull points all depend on both disciplines working from the same dimensions at the same time.
Research on project delivery supports the value of fewer handoffs. A Construction Industry Institute and Charles Pankow Foundation study of 212 projects, summarized by the Design-Build Institute of America, found that design-build projects averaged 3.8% less cost growth and 1.7% less schedule growth than design-bid-build projects. They were also 36% faster during the construction phase. The study covered buildings and infrastructure broadly rather than solar specifically, but the mechanism applies. When one party is accountable for both design and construction, fewer assumptions go unchecked.
The same logic shows up in battery storage. In its work on storage failures, EPRI has recommended system-level analysis with particular attention to the interfaces between components, according to EEPower’s coverage of the 2025 Solar Risk Assessment.
4. Electrical equipment gets ordered after the schedule is set
Transformers and switchgear now set the pace on many projects. Citing PwC analysts, pv magazine USA reported in May 2026 that lead times for high-capacity transformers have reached as long as four years. The article cites Wood Mackenzie data showing that demand for generator step-up transformers rose 274% between 2019 and 2025, and industry experts quoted in it put price increases at roughly 80% over five years. Medium-voltage switchgear is affected as well. Environment+Energy Leader reports, based on Wood Mackenzie data, that some medium-voltage equipment now takes more than a year to arrive.
Import dependence adds exposure. Since 2019, imports have supplied an estimated 80% of U.S. power transformers and 50% of distribution transformers, according to Wood Mackenzie data cited by pv magazine USA. New foreign entity of concern (FEOC) sourcing rules add compliance questions to equipment selection.
The largest lead times apply to utility-scale equipment, and commercial projects often use smaller units with different timelines, so quotes should always be confirmed with manufacturers. The principle holds at every size. Equipment selection is a design decision that sets pad dimensions, trench routing, protection settings, and commissioning sequence. When the choice is made late or changed late, the rework lands on civil and electrical crews at the worst possible time.
5. Tax credit deadlines leave less room for every other problem
The federal solar investment tax credit now runs on a fixed clock. Under the One Big Beautiful Bill Act, projects that began construction by July 4, 2026 have until the end of 2030 to be placed in service under continuity rules, while projects that did not must be in service by December 31, 2027, as summarized by Tax Equity News. Federal guidance also tightened how developers demonstrate a construction start and centered the test on physical work. As of this writing in October 2026, a project that missed the July date has roughly 14 months to finish.
Every risk described above becomes more costly under that kind of schedule. For a project facing the 2027 deadline, a slip of a few months in interconnection or equipment delivery can affect whether the project qualifies. Owners should confirm their own position with tax counsel, and contractors should treat these dates as hard constraints when they build a schedule.
6. Underperformance often traces back to decisions made before commissioning
kWh Analytics, which specializes in solar risk and insurance, analyzed 34,000 system-months of operating data from 2015 to 2023 and found that U.S. solar assets produced 8.6% less energy than their original forecasts. Those forecasts are called P50 estimates, meaning the production level a project is expected to meet or exceed half the time. Financing is often sized against them.
The report did not isolate a single cause. According to EEPower’s summary, monthly operating reports lacked the detail needed to identify root causes. Possible contributors included optimistic availability assumptions, inflated P50 values, and underestimated losses from weather, curtailment, shading, and DC-side problems. The 2026 edition adds that thermal drone inspections, a standard tool for finding module defects, often miss balance of system problems that produce no measurable heat before they fail. Balance of system means everything other than the modules, such as wiring, combiners, inverters, and transformers.
These findings do not blame construction quality directly, but they point to a practical conclusion. Systems built with documented QA/QC, tested thoroughly at commissioning, and maintained by people who understand the electrical side of the plant are easier to keep at forecast. A contractor who remains responsible for performance after energization has a reason to care about those details during construction.
What a long-term partner does differently
The problems above share a pattern. Each is cheap to address early and costly once construction is underway. A partner that stays with a project from planning through operations is positioned to catch them, and in practice that comes down to proactive, early engagement and treating procurement as part of the design.
To learn more about working with a company that works efficiently to keep your projects on track, get in touch.